Lamberts Point 26th Street Improvement
BIDS WILL BE RECEIVED AT:
201 Granby Street, 7th Floor, Purchasing Department (ONLY)
no later than 3:00 p.m. Eastern Standard Time on
Thursday, 11 February 2010
Bids will be opened at 3:15 p.m. and read aloud in the 12thfloor conference room at the same address.
NOTE: VENDORS, DELIVERY YOUR BIDS TO THE 7TH FLOOR! YOU WILL BE DIRECTED TO THE 12TH FLOOR AFTER FOR THE OPENING.
Question and Answers
Question 1 - The bid units for this project does not reflect any pipe work but the plans show some pipe work. Is there any pipework in this project?
Answer 1 - This project includes pipe work consisting of new water, sanitary sewer, and storm sewer mains and services. The project is being bid lump sum and unit price items are included only for those items that may be potentially added to the contract at the NRHA’s discretion. All pipe work is included in the lump sum bid.
Question 2 - Are the unit prices on the bid form for additional work? We think they are, but it does not read that way. It could be interpreted that the base bid includes only the items not covered by unit prices for bidding purposes (page 16 of 135).
Answer 2 - The project is being bid lump sum and the base bid should include the entire scope of work as indicated on the plan set. The unit price items are included only for those items that may be potentially added to the contract at the NRHA’s discretion.
| Attachment | Size |
|---|---|
| PR251-269-10 Drawings 1 of 2.pdf | 4.43 MB |
| PR251-269-10 Drawings 2 of 2.pdf | 6.31 MB |
| PR251-269-10 Project Manual Part 1.pdf | 7.12 MB |
| PR251-269-10 Project Manual Part 2.pdf | 1.28 MB |
| Add 1 Form of Bid.pdf | 25.56 KB |
| Add 1 SKCs.pdf | 559.83 KB |
| Add 1.pdf | 21.7 KB |